Now we will study "Time Log" List

Add a new item in clicking on the "Multiple Paper" icon

You enter the date, the person, a small description of the activity, the cost and the cost type to have an idea of what you have spent in using this ressource.

This cost management is different from the task costs, this allows you to manage it independently of the orders and the tasks.

You can assign a task to this time log in clicking on the "Tasks" button. In this case QuickP will recalculate automaticly the "Done Load" field of this task according to the Workload unit. If the workload unit is in days, QuickP will use the value given in the "Workload Pref" Menu !

In this case, a day is 8 hours !

WARNING: You will have to reajust manually the rest to do to get the real progress percentage of the task, in going into the associated task.

Click on the 'Keys Dates' to adjust the duration of work.

So I've worked on this task during a day !

Click on "Tasks" button, QuickP will display all the tasks for the current project, select one and click OK. If you want to unselect the previous task and not assign a task click on the "NONE" button.

Click on OK !

Have a look on the associated task in the task list.

We had before 48 in the "Already Done" field, we have now 56=48+8

Let's return to the Time Log list

If we click on the "Stats" button, QuickP will display a dialog box where you can enter the period, and if you want the name of the person even the activity to calculate the time spent and the costs.

Here is the result

Let's see the "Stop!" button

This button is used to modify directly the key dates.

The End time is automaticly changed to the current time.